3.2 DISCHARGING CLEAN BALLAST (CBT TANKER)
CBT ballast is normally discharged after the tanker is safely berthed
and before cargo loading operations commence. The ballast piping should
have been prepared according to the ship's operating procedure, an example
of which is provided in section 2.23
of this manual.
The oil discharge monitor must be functioning and the system ready in
all respects to monitor the ballast discharge. All cargo and ballast
tanks, including slop tanks, must be open to the inert gas main, with
tank IGS isolating valves locked or lashed open. All cargo and slop
tank gauging openings must be closed. The inert gas main must be isolated
from open mast risers and high velocity vents. The IGS deck isolating
valve must be open and the IGS plant producing gas with oxygen content
of 5% or less.
Following the guidelines of the IMO publication Dedicated clean
ballast tanks, (1982 edition) (see section 2.2.3
of this handbook), the clean ballast discharge procedure would be:
1 Open valves for discharging ballast.
• No.1 cargo main valves nos. 40, 41, 59, 60,
104, 144 and 123.
• No.1 discharge main valves nos. 155, 156 and
127.
• No.2 dedicated clean ballast tank nos. 36,
37.
• Starboard sea suction valve no. 115.
2 Start the No.l pump and begin discharging ballast
overboard. Observe the indications of the oil content monitor and the
appearance of the water surface near the overboard discharge.
3 Discharge the No.2 clean ballast tank until the tank
innage is 0.5 meter; then close valves nos 36 and 37. (This retains
enough water in No.2 centre tank to flush the branch pipes when the
lines are being cleaned later.)
4 Discharge the No.4 dedicated clean ballast tank until
the tank innage is 1.5 meters, then stop the pump and close valves nos.
58 and 67.
5 Drain all ballast piping to the port slop tank.
6 Close all valves.
During the discharge of ballast, if there is any doubt regarding the
cleanliness of the water, the overboard discharge must be stopped and
the remainder of the ballast retained on board or discharged ashore.
3.2.1 Simultaneous loading and CBT ballast discharge
Occasionally, trim or freeboard restrictions prohibit the complete discharge
of CBT before cargo loading begins. CBT ballast may be discharged during
the loading of cargo either simultaneously or by interrupting the loading.
There must be effective two-valve separation between the cargo piping
and the clean ballast system. The master is responsible for ensuring
that the separation valves are leak tight.
Simultaneous loading and de-ballasting can also be safely conducted
where the cargo tanks are fitted with individual cargo loading lines,
not connected to the discharge piping.
Until sufficient clean ballast has been discharged to complete loading
operations, the CBT system piping must be kept clean.
Simultaneous cargo loading and ballast discharge reduces both the port
time of the vessel. It also reduces the total volume of hydrocarbon
emissions produced by the loading operation, since the atmosphere displaced
by cargo entering the cargo tanks is transferred through the vent system
to the ballast tanks as ballast is discharged.
However, the reduction in air pollution is achieved at some increase
in risk of sea pollution. For the owner's protection, it is always better
to conduct the de-ballasting and the loading operations one at a time,
when possible.
3.2.2 Alternate de-ballasting and loading
If company or terminal policy prohibits simultaneous de-ballasting and
cargo loading, then the vessel may load part of the cargo, stop loading,
de-ballast and then complete cargo loading. While the vessel is loading,
the ballast tank levels must be carefully monitored and while it is
de-ballasting the cargo tank levels must be closely monitored.
|