3.25 LOADING WHERE DRAFT OBSERVATIONS ARE NOT AVAILBLE
Completion of loading may take place in a number of circumstances
where the draft of the vessel cannot be observed, or cannot be reliably
observed. Normally such situations apply to straight cargoes of crude
oil only and the following recommended procedures assume this to be
the case. In these cases it is essential that the following be determined
to the greatest possible accuracy:
The specific gravity of the cargo being loaded.
The temperature of the cargo loaded into the tanks.
The quantity of fuel and water on board.
The ship will be loaded by calculation, that is, the weight of cargo
allowed on board must be very closely calculated, with appropriate allowance
for the vessel's experience factor and for the sag normally observed
when fully loaded. When loading by calculation the salinity differential
is not considered. The salinity differential allowance can only be used
where the draft can be observed and the vessel is fully afloat.
Loading by calculation includes the following steps:
Determine the controlling/limiting draft mark.
Deduct the anticipated sag to determine the calculated
mean draft.
Determine the corresponding deadweight tonnage for the calculated mean
draft.
Deduct tonnages of fuel, water and stores on board to determine the cargo
tonnage available.
Multiply the available cargo tonnage by the factor for cubic meters per
tonne corresponding to the cargo gravity; the result is the net volume
of cargo to be loaded.
Divide the net volume by the cargo temperature correction
factor normally used to convert from observed loading temperature to
net volumes at 15 °C (60 °F); this gives the anticipated gross volume
to be loaded.
Multiply the gross volume by the ship's experience factor
to obtain the volume to be loaded as measured in the ship's cargo tanks.
As the vessel loads, samples of the cargo should be drawn and the
specific gravity measured and corrected for observed temperature. Two
or three samples should be taken over the period of the bulk of the
loading period to verify a uniform gravity or obtain an accurate average.
If the observed gravity differs from that used to calculate the load,
revise the calculation using the observed gravity.
Cargo temperatures should be measured for each tank when they have been
topped off and the net tonnage in each tank calculated separately. The
actual loaded temperature should be used to revise the earlier calculation.
When the vessel is loading trim tanks, the calculations of all completed
tanks are verified and the volume to be loaded in the trim tanks is
computed. The ship loads until the trim tanks have reached the calculated
ullage level. If the ship is provided with automatic draft sensors,
the chief officer may use them, provided he is confident of any correction
factor to be applied to their indications and provided he stops the
loading at the desired draft when indicated by the sensors, or on reaching
the calculated cargo volume, whichever occurs first!
3.25.1 Loading 'over the tide'
Loading over the tide is a procedure employed where ships load at a
berth where there is adequate water depth for the ship fully loaded
only at certain stages of the tide. Such berths normally have a significant
tidal range and a relative freedom from weather induced tidal variations.
In loading over the tide timing is everything. The ship and shore terminal
must be ready in all respects to conduct the loading operation when
it arrives at the terminal and all formalities and preparations must
be suitably manned and streamlined to minimise the time between all
fast and commence loading. Preparation of a time-bar diagram of the
loading procedure is essential to determining the time the ship will
need to complete the necessary operations. (See section 2.20.5).
Where the tide is diurnal the ship is berthed at a time when it can
safely load and depart on the next flood tide.
Where tides are semi-diurnal, there will rarely be enough time to permit
the ship to load and sail on a single tide. In those cases one of two
alternatives must be used. The first occurs when the ship attempts to
complete loading before the next fall of the tide, but some delay or
interruption interferes. The ship is now too deeply loaded to lie in
the berth safely afloat through the next low tide. There is no choice
then but to disconnect and unmoor the ship, to proceed to a safe anchorage
and await the next rise of the tide. When the berth again has adequate
water, the vessel returns, reconnects and completes loading.
An alternative procedure is to accept that the vessel will not be able
to sail on the high tide following the start of loading and to stop
the loading while the ship still has adequate under-keel clearance to
lie safely afloat through the following low tide. The ship waits until
the low tide has passed, plus a reasonable interval and then resumes
loading. In this case the chief officer must closely calculate the rate
at which his draft will increase with the normal shore loading rate
and compare this against the rate of increase of the water level in
the berth following low tide. It is possible for some terminals to load
a tanker faster than the tide will rise and the ship may thereby be
put on bottom if loading is resumed immediately after the time of low
water. The chief officer should wait until he has a positive indication
that the tide is flooding before agreeing to resume loading. He should
personally observe the tide board/gauge in the berth to confirm the
start of the flood before opening his loading manifold. The tanker completes
loading in the normal way and endeavours to depart on the last of the
flood tide.
Because any errors made in this procedure could result in stranding
the vessel with pollution consequences, the practice of loading over
the tide is generally not accepted by major oil companies or concerned
charterers. 'Safe berths' are now considered to be those which the vessel
may safely proceed to, lie in and proceed from, always afloat.
3.25.2 Loading on bottom
The first part of this section described a procedure which may be used
to load a tanker where the draft cannot be directly or accurately read
at all. In some berths, a vessel may be directed to load cargo to a
draft exceeding the available berth depth. This is seldom done with
chartered vessels as voyage or time charters call for the vessel to
be operated 'always afloat' and to call only at docks in safe ports
where they may 'proceed to, lie at, and proceed from always
afloat'.
However, the regulatory and environmental impediments to dredging, particularly
in the United States have resulted in many berths being silted to less
then normal tanker drafts at the face of the dock. The sediment is soft
and uniform and is harmless to the hull if the ship is loaded to only
a few centimetres deeper then the berth face depth. In the US Gulf coast,
there is usually too little tidal range to either strand the vessel
hard, or to permit loading 'over the tide'.
To complete loading at such a berth, the chief officer must accurately
determine the water depth that will be available at the berth face about
the time he is completing the loading operation. It is advisable to
take soundings along the inboard side of the ship after berthing to
confirm any information supplied by the terminal.
The ship is loaded in the normal way until its draft is slightly less
than the berth depth. The chief officer observes the forward, aft and
amidship drafts closely, measures the salinity of the berth water and
verifies the cargo gravity and temperature as indicated in section 3.25.
The chief officer then calculates the quantity of cargo needed to put
the ship down to its marks and trimmed to an even keel. Loading is completed
without further inspection of the draft marks, for when the ship takes
the bottom and begins to list slightly the draft readings will become
useless.
Tank gauging is complicated by the slight list and appropriate corrections
must be made when calculating the quantity on board. When inspection
formalities are complete, the tugs are used to pull the vessel off the
berth. Immediately she is afloat and before she begins making way, the
chief officer will have an opportunity to accurately read his amidship
draft and verify the accuracy of his loading calculations.
|