5.19 STARTING THE DISCHARGE
The cargo discharge operation is the culmination of the tankers work.
After diligently preparing the tanks for cargo, carefully loading the
cargo and exercising proper care and custody during the loaded passage,
the crew needs only to get it safely ashore to complete their mission.
However, the discharge operation offers more opportunities than the
loading operation to have a cargo incident, including a spill! Only
the diligent application of all necessary precautions will get the cargo
into the shore tanks without accident.
Case study
A crude oil carrier berthed at a Thames refinery on a clear day in December.
The arrival, berthing and inspections were without incident. Shortly after
10.00 hours, the ship began discharging cargo. About ten minutes after
cargo discharge began, the cargo officer noted a sudden increase in discharge
pressure. He reduced the pumping rate to bring the manifold pressure below
maximum limit and called the chief officer. Almost immediately, the deck
watch called to advise that one of the cargo tanks was overflowing. The
cargo officer stopped the pump and closed tank valves. The deck watch
was directed to close the manifold valve. About 400 litres escaped onto
the deck and 40 litres overboard. All oil was recovered by vacuum lorry.
An immediate investigation discovered that ten minutes after the ship
had begun discharging, the shore terminal had started an intra-terminal
transfer. The terminal valve alignment was incorrectly set and the high-pressure
shore pump began delivering oil into the dock receiving line and onto
the ship. Case analysis
While the shore terminal is clearly at fault in this case, the incident
raises doubt about the efficiency of the vessel's main discharge line
nonreturn valves. It is a good example of how nothing can be taken
for granted during any cargo transfer. At the beginning of the
discharge operation, the tanker typically has very little ullage space
in the tanks which are first to be pumped. If there is an error in the
alignment on the ship, an incorrect alignment of the shore booster pump,
a defective check valve on the dock, of a pumping error on the shore,
it can take only a few seconds for the ship's tank to be filled to overflowing
by the unexpected entry of cargo.
These incidents are best avoided by:
• Using written cargo system lineup orders and double-checking the setting
of all valves.
• Being extra vigilant during the first minutes of the discharge operation
to ensure that the oil is moving out of the ship, not in.
• Whenever possible, start the cargo discharge by pumping a slacktank,
so that additional ullage space is available to accept and detect an
incorrect cargo flow.
5.19.1 Starting communications
The ship-shore communications before start of discharge should reflect
the example for the loading operation in section 3.16.
The requirement is for short, clear, precise statements of the intentions
and readiness of each party in the cargo transfer, conducted in a way
that indicates without doubt when the ship can start its cargo pumps.
5.19.2 Starting cargo pumps
The typical cargo pump installation on a traditional tanker includes
from two to four steam turbine driven centrifugal cargo pumps. The turbines
are located and started in the engine room and they drive the cargo
pumps (located in the pumproom), by shafts passing through gas-tight
seals in the intervening bulkhead.
When the shore has declared that they are ready to receive cargo with
all valves open, the pumpman will be directed to open the pumproom bulkhead
and/or pump suction valves and flood the pump with cargo. The pump casing
vent line should be used to verify that the pump is filled with cargo
before it is started. When the pumpman advises the chief officer that
the pump is ready to start, the cargo officer, or first officer, calls
the engine room for the pumps to be started. Normally, the watch engineer
starts the cargo pump turbine in the engine room. He runs it at slow
speed for a few minutes until satisfied with its operation, then assigns
control of the turbine/pump speed to the cargo control room control
panel.
After pump rotation starts, the cargo officer opens or causes his watch
personnel to open the correct manifold valve. The pumpman continues
to monitor the performance of the pump, while the cargo watch officer
must monitor the ullages of the tanks being pumped. When it is apparent
that cargo is being discharged (tank ullage increases), the ship advises
the shore terminal operator. When the shore terminal operator confirms
that cargo is being properly received, then the pumpman or cargo watch
officer can begin increasing the pump speed and discharge pressure up
to the maximum permitted. This should be done in steps, permitting the
pumpman and deck watch personnel to make several checks of the machinery,
piping and shore connection as the pressure increases. If more pumps
are to be used on the same shore line, the first pump(s) should be brought
to only moderate speed until all pumps are on line, after which they
can be brought up to speed in parallel.
Immediately after the start of the discharge, all inactive tanks must
be checked to verify that their ullage is constant and particularly
that it is not decreasing (tank filling up).
During this first hour of discharging, frequent inspections of the pumproom,
other non-cargo spaces, the water surface in the berth and the deck
piping should be made to permit early detection of any malfunctions
or leaks.
On ships equipped with electrically driven deepwell pumps, it is important
to ensure that the drive motor is started in the low speed range and
the pump allowed to stabilise before increasing speeds to the maximum
permitted. Ships equipped with deepwell pumps utilise their deck loading
lines as discharging lines. Because of this arrangement, it is important
to keep the tank discharge valves on all tanks closed until immediately
before that tank is ready for discharging.
5.19.3 Starting against back-pressure
Some discharging terminals have an unavoidable level of back pressure
which the ship must overcome before cargo will begin moving ashore.
At these berths, unless the chief officer has absolute confidence in
the shore and /or ship check valves, the manifolds valve should not
be opened until the ship's pumps are producing a discharge pressure
equal to the shore back-pressure. An accurate determination of the shore
back-pressure must be made before the pump is started. The cargo pump
is then started and increased in speed until the manifold pressure equals
the shore pressure. The manifold valve is then opened and the pump speed
increased, all the while carefully watching the ullage of the first
cargo tank being discharged.
During the start to the discharge, the pumpman or cargo watch officer
must be ready to immediately shut off the cargo pumps and manifold valve
if a leak or misdirection of flow is detected.
If the shore terminal offers booster pumps to assist with discharging
against high back-pressure, then the cargo discharge should be started
at moderate speed, observing the pump discharge pressure carefully.
If the pressure decreases suddenly after a few minutes, it is an indication
that the shore booster pumps have been started correctly. If the discharge
pressure suddenly increases the cargo watch officer must immediately
call the shore terminal asking them to stop the booster pumps. The sudden
pressure increase is an indication that the valve alignment of the booster
pump(s) may have been reversed, causing the booster pump to deliver
cargo toward the ship instead of to the shore tanks.
When booster pumps are in operation, indicate this fact in the logbook
as an explanation of low ship discharging pressure (to defend against
any later claim by charterers that ship was unable to maintain charter
pumping pressure while discharging).
5.19.4 Shore line displacements
Shore line displacements are conducted for two main reasons:
1 To displace the product already in the shore pipeline,
in which case this is normally a shore stop. Portland, Maine is a terminal
at which pipeline displacements are routinely required.
2 To verify that there are no voids in the shore pipeline
contents for cargo loss control purposes. These displacements are normally
a ship stop.
The chief officer should take special interest in the line displacement
operation, particularly where the reason is for loss control purposes
and additionally:
a Confirm the accuracy of the independent or terminal
surveyor's
calculations for the line displacement.
b Monitor the remaining tanks on the ship in case product
has
entered or escaped to/from any other tank(s).
c Obtain a copy of the calculations of the quantity
received ashore.
Despite numerous theories regarding temperature corrections for shore
line displacements, the line displacement volumes should be documented
uncorrected for temperature.
The shore terminal may request that the ship begin the discharge by
displacing the shore pipeline, giving the amount of displacement required.
The chief officer should request to know the grade of petroleum being
displaced and whether the ship will be requested to stop the discharge
at the end of the displacement.
To assist the shore terminal in accurately completing the line displacement,
the ship should conduct it by discharging from a single tank which does
not change the trim or list significantly and should calculate a stop
gauge for the tank used (remembering to allow for the fact that the
ship's deck lines are empty when starting cargo).
The chief officer should advise the shore terminal operator when they
are nearing the displacement quantity requested and again tell them
when it is reached, but should not stop the displacement unless instructed
to do so by the shore terminal. The cargo pump should be run at the
agreed speed throughout the line displacement, without speed changes.
Enter the times and ship tank ullages for starting and completing the
line displacement in the logbook.
5.19.5 Stripping tank water bottoms
If the vessel has significant water bottoms in the cargo tanks, the
master should suggest to the terminal, in writing, that the water bottoms
and slops be discharged first to a single shore tank to minimise the
possibility of spreading the 'wet bottoms' throughout the shore tank
system. The shore may request that this be done in any event, particularly
if the cargo is home heating fuel. If this operation is to be conducted,
the ship should be trimmed and listed as necessary for stripping and
the water stripped from the tanks, discharging to the main cargo line.
When all water bottoms have been stripped, the main cargo pump can be
started.
If the main cargo pump is used to remove wet bottoms with the ship on
an even keel, it may take up to one meter of cargo pumped from each
tank to discharge 5 centimetres of free water bottoms. Several tanks
with similar ullage should be opened first to reduce the drawing off
rate from each tank. Forwardmost tanks should be dealt with first to
improve the trim as the decanting progresses. De-bottoming by discharging
one tank at a time with a MCP is generally not a successful operation.
5.19.6 Maximum discharge pressures and rates
The maximum permitted discharge pressure will be set according to the
limits of the shore terminal or the ship, whichever is lower. The ship's
maximum pressure limit will be as read on the gauges at the discharge
side of the pumps. Pressure should always be built up gradually, with
frequent visual checks of pumproom and deck piping and the manifold
connections.
Initial pumping rates for static accumulator oils will be limited to
those producing linear pipeline velocities of less than one meter per
second (see section 7.4.5 of the International safety guide for
oil tankers and terminals).
The shore terminal may request reductions in pumping rates for topping
shore tanks or other reason. These requests should always be accommodated
immediately and the shore terminal operator advised when the rate has
been reduced. Enter the request and time of reduction in the log book.
Also enter the time full pumping rate is requested and resumed.
5.19.7 Discharging to floating-roof tanks
Crude oils and gasolines will normally be stored in shore tanks with
internal floating roofs ('floaters'). When these shore tanks are empty,
the roof is supported one or two meters above the tank floor by numerous
'legs'. High velocity flow of cargo into empty 'floaters' can cause
extensive damage to the floating roof, especially if constructed of
aluminum. Normally the shore will request that discharge to empty 'floaters'
proceed at a reduced rate until the roof is well afloat. This request
should be strictly complied with and the time of reduced pumping rate
entered in the log. Do not increase the rate until advised to do so
by the shore terminal operator.
5.19.8 High vapour-pressure cargo
High vapour pressure cargo can be difficult to discharge efficiently
and failure to follow some normal procedures can result in prologued
cargo discharge and large ROB.
All cargo handling equipment must be in good working condition and well
maintained. The pipeline and valve system must be leak free. The following
procedures are recommended:
• If the vessel is fitted with vacuum pumps, primavac systems, eductors,
stripping pump(s) and separate stripping lines then this equipment should
be used.
• If the cargo pumps are fitted with a priming line to the stripping
pump, this should be used to draw off the gas generated in the main
pumps, thus improving suction. The vacuum pump should be used in the
usual way.
• When the tank has been discharged to a level below that of the pump
intake (ie. when the pump has a negative suction head), the main cargo
pumps, vacuum pumps and primavac systems should be closed down. The
final stripping should be carried out by the eductor and/or stripping
pump. The RPM of the pump driving the eductor must be reduced to avoid
a top low vacuum which will cause gassing at a higher liquid level in
the cargo tank. For the same reason, the stripping pump should be carefully
watched and slowed down when necessary.
• Put one pump only on each cargo system; do not make the suction lines
common.
• If necessary, the cargo pumps should be run at reduced RPM. This will
be a deviation from the normally preferred procedure of shutting down
a pump and keeping the others at full speed.
• Retain one tank at a level sufficient to provide drive for the eductors
and priming liquid for the pumps. There is an advantage in using a forward
tank for priming. With the vessel trimmed by the stern, a positive head
to the pump is achieved at all times. This can only be done if hull
stresses and stripping requirements permit.
• If eductors are fitted, use the smallest tank possible (e.g., a slop
tank with its own stripping line) to provide the eductor drive fluid.
This tank should be discharged last and is likely to be extremely difficult
to drain. When suction is lost the cargo remaining will be substantially
less due to the small size of the final tank.
• As a means of recovering as much cargo as possible, the tank can be
pressurised with inert gas. However, do not close the P/V valve, as
this can overpressure and rupture the tank. Place the P/V valve in the
automatic mode. The tank pressure must be carefully monitored by use
of a gauge or manometer. The pressure must not be allowed to exceed
2 psi. In a vessel without IGS, low pressure air may be used, but not
more than 2 psi. Reduce tank pressure to normal operating level as soon
as discharge is complete. This procedure should not be used as a substitute
for maintaining pumping equipment and cargo lines in good condition.
• Maintain the vessel with the maximum practicable stern trim. Maximum
trim is normally restricted by the amount of trim which the boilers
an other machinery can accept without malfunction or damage.
• Do not allow the oil level in one tank to get out of step with that
in another if more than one pump is discharging into the same riser
or hose. Failure to monitor tank levels can result in unbalanced pumps
and loss of suction. This is due to the pump drawing from the lower
level tank being unable to discharge against the discharge head from
the pump connected to the higher tank.
• Reduce the RPM of the pumps at approximately half tank level. Thereafter,
reduce the flow as the ullage increases. Throttle in (partially close),
the pump discharge valve to maintain an adequate back-pressure (80 to
100 psi at the pump). Eventually the flow rate may be reduced by as
much as 90% of the rated capacity of the pumps.
• Do not throttle in the suction valve at any time until the final stages
of discharge.
• If suction is lost, the pump must be primed from a tank with a positive
head and the RPM further reduced. In most cases, the pump must be stopped
before it can be properly primed.
|